Links ====== .. index:: Links **Goal:** you check and edit cross-project links, resolving time conflicts between linked projects. |image0| Cross-project links differ from normal links in two ways: - The successor project is not shifted automatically if the predecessor project's finish date moves. Instead, a delay (negative or positive) is set. - In addition to the delay, a cross-project link has a time reserve: after linking two projects, a time difference between the end of the predecessor and the start of the successor is considered not only as a delay but also as a reserve. Here you can check and edit the cross-project links. |image1| You can set a time frame or enter a search term in the **Filter** field for the **Project/Activity** columns. Functions ------------ |image2| - **Status accepted** (|image3|) - **Conflict message** (|image7|) - **Shift successor** (|image4|) - **Correct delay by reserve** (|image6|) - **Revision history** (|image5|) **Status:** the **Status** column shows whether time changes related to the start or end of the cross-project links occurred, or whether conflicts arose. Example: resolve a time conflict ------------------------------------- 1. You created a link between two planned projects with a negative delay, because the second project starts earlier than the first project ends. |image8| 2. A time shift occurs in the first project: the predecessor ends 7 days later than originally planned. |image10| The value in the **Reserve** column shows by how many days the original plan has changed. **Red** indicates a growing time deficit, **green** indicates a gained time reserve. 3. Via the **Shift successor** icon button (|image4|), the dates of the successor project are shifted by the value of the reserve. |image12| The next time the portfolio is opened in Rillsoft Project, you get a message about the date changes in the successor project. Further functions --------------------- **Revision history:** use the icon button (|image5|) to see the history of the link. |image9| **Correct delay by reserve:** use the icon button (|image6|) to recalculate the delay based on the reserve. Check the result ----------------- After resolving a time conflict, the **Status** column shows that the link is accepted again, and the date change is visible in the successor project. Related topics -------------- - :doc:`project` - :doc:`portfolio` - :doc:`02-task-oriented-help/share-projects-and-portfolios/index` .. |image0| image:: ../images/link.png :alt: Open the "Links" menu item .. |image1| image:: ../images/link_filter.png :alt: Selection criteria and filter for the links list .. |image2| image:: ../images/link_action.png :alt: Overview of functions for cross-project links .. |image3| image:: ../images/link_status.png :alt: "Status accepted" symbol .. |image4| image:: ../images/link_project_move.png :alt: "Shift successor" icon button .. |image5| image:: ../images/id_project_version.png :alt: "Revision history" icon button .. |image6| image:: ../images/link_reserve_save.png :alt: "Correct delay by reserve" icon button .. |image7| image:: ../images/link_conflict.png :alt: "Conflict message" symbol .. |image8| image:: ../images/link_delay_1.png :alt: Cross-project link with negative delay .. |image9| image:: ../images/link_revision.png :alt: Revision history of a link .. |image10| image:: ../images/link_delay_2.png :alt: Time shift in the predecessor project with a reserve value .. |image12| image:: ../images/link_delay_4.png :alt: Shifted dates in the successor project after reserve compensation